Required input for feasibility study on PV project PART 1 Meteorological Data 1.1
Find the typical and long-term meteorological station, which nears by the potential site l
Collect the general condition of the observation station, including the type, location, elevation, surroundings and the impact by the surroundings of the radiation observation instruments Result: got the “climatological data for the period 1981-2000”, from the station Kamphaeng phet. l
The history of the meteorological station, such as the status of the surroundings; the change information of the location and the radiation observation instruments Result: no information. 1.2
Collect the data of the mentioned meteorological station or the other long-term data, including: 1)
Key characteristic values of atmosphere: l
Mean temperature l
Extreme max temperature l
Extreme min temperature l
Max temperature l
Min temperature, l
Mean rainfall l
Mean evaporation l
Max depth of frozen ground l
Max snowpack depth l
Mean wind speed l
Prevailing wind and occurrence time l
Max wind speed Result: could get the input from the “climatological data for the period 1981-2000” 2)The mean monthly temperature within 30 years. Result: could get the input from the “climatological data for the period 1981-2000”, but for 20 years. 3)The numbers of disastrous days within 30 years l
Sand and dust weather l
Haze l
Fog l
Hail l
Thunderstorm l
Squall Result: could get the input from the “climatological data for the period 1981-2000”, but for 20 years. 4)Monthly radiation data and sunshine duration (hours) within 30 years Result: No information from the station, but got the NASA data. 5)与项目观测站同期完整年逐时(或更短)的太阳辐射资料(含直接辐射、散射辐射、总辐射资料); Result: No information from the station, but got the NASA data. 6)项目现场太阳辐射观测站至少连续1年的逐分钟太阳能的总辐射、直接辐射、散射辐射、气温等的实测时间序列数据; Result: No information from the station, but got the NASA data. 7)Flood data Result: got a pdf map, but it is in Thai. PART 2 Other Data 2.1 County annals Result: No information. 2.2 Planning of the potential site and pre- feasibility study work product Result: No information. 2.3Topographic map—Auto CAD file l
Measurement accuracy: no less than 1:5000; 1:2000 or 1:1000.is better. l
The map shall show elevation of each contour line, location and name of railway, road, country, lake, wet land, and river and so on. Result: can only get the 1:50000 drawing. 2.4 Soil condition Result: No information. 2.5 Physical geography of the potential site, including: l
Transportation status to the site(Accessibility of roads to the site) l
Dust status and the distribution of other pollution sources Result: No information. 2.6 光伏发电工程所属地区社会经济现状及发展规划、太阳能发电发展规划、电力系统概况及发展规划、电网地理接线图、土地利用规划、自然保护区和可利用的消防设施等资料。 2.7 The evidence to prove that the photovoltaic project already obtained the access to power system from PEA. Result: can got the certificate from the partner recently. 2.8 The price of main construction materials and relative documentations and regulation on cost estimation. Result: No information. 2.9 Grid connection requirements Result: 2.10 Sub-station n
Distance of sub-station to site n
Pre-approval by PEA that the sub-station can take the expected upload of the installed capacity, if needed. n
Confirmation by local authorities, if needed n
Information of the transmission lines, names, capacity, access point to the grid… Result:
|